The Proposed Hudson Logistics Center Sound Study Summary & Links to Hillwood's Study and Peer Review


This post highlights the sound study, peer review, and responses related to the Hudson Logistics Center proposal.


Requirements

As part of the site plan review, the applicant must make adequate provisions for the elimination of undesirable and preventable elements of pollution, such as noise (§275-6H).  Additionally, Hudson town code prohibits anyone from creating noise pollution (as defined by §249-2)  and sets some specific limits, including (§249-4):

  • Continuous noise limits, depending on receptor land use and time of day

  • Separate impulsive (short duration) noise limits, also depending on land use and time 

  • Restricts the amount of increase in background noise

  • Prohibits producing a pure tone

  • Restricts the times and days allowed for construction


Ostergaard Acoustical Associates (OAA) Study

18 May 2020


Reviewed Hudson code to determine a noise goal.  Noted the different noise limits in daytime vs. nighttime and residential vs. industrial use, as well a limit on the noise increase.  Set maximum noise limit equal to average noise requirement in attempt to ensure compliance.


Recommended project mitigation features include an earthen berm or sound wall as allowed by the presence of wetlands, use of certain types of tractor back-up alarms, and HVAC equipment in line with the assumptions used for modeling.


Used acoustical modelling software to predict noise levels at ear-level for nearby locations after development.  Noise sources include rooftop HVAC and truck activity at select locations.  Results indicate maximum noise levels at, or just above, required average levels, which the study states “meets the intent of the project goal”.


Peer review by Harris Miller Miller & Hanson Inc. (HMMH)

29 June 2020


Identified deficiencies with OAA sound study including:

  • Noise from truck travel close the residences was not included

  • Existing ambient noise levels were not measured to determine the expected change

  • Potential for a pure tone condition was not evaluated

  • Noise during construction was not addressed

Concluded that the applicant did not fully demonstrate there will be no negative noise impact.


OAA response to peer review and some written comments

13 July 2020


Described changes in the project that impact noise levels:

  • Buildings on lots B and C were each moved north, further from abutting residences

  • Updated HVAC equipment location and quantity to be more accurate

  • Improved earth berm with a sound wall to be placed on top in portions

  • Emergency generators added to each building, which sometimes contribute to noise

Responded to HMMH comments:

  • Argued that noise from truck travel is lower than other sources

  • Agreed to deploy long-term sound level monitors to measure ambient noise

  • Provided preliminary data based on similar facilities that a pure tone condition will not exist

  • Regarding construction noise, stated that project will conform to §249-4I of town code, which restricts construction to certain times

Also responded to a large number of written comments that had been sent to the Planning Board.


July 22 Planning Board Meeting

Benjamin Mueller, who prepared the OAA study and response, presented remotely, which can be viewed at the following link starting about 24 minutes in.

http://www.hudsonctv.com/CablecastPublicSite/show/9222?channel=3

  • Summarized existing reports and status

  • Acknowledged impulsive limits in town code

  • Increased height of shielding (berm and wall) to address concerns at different elevations nearby

  • Mitigation measures continue to be refined and improved


Later during discussion, Selectman Marilyn McGrath noted multiple neighbors made complaints about the noise produced by drilling performed at Green Meadows on a weekend in June in violation of town code.  Justin Pasay, a lawyer for the applicant, said that they would address that.


Outstanding Concerns

Questions and concerns regarding noise remain, including:

  • In addition to abiding by the allowed hours for construction set in §249-4I, construction noise should meet the requirements throughout §249-4, which won't have the benefit of the berm and sound wall during their creation.  This noise should be estimated.

  • The sound study identifies Sam’s Club as an industrial use where it is clearly a business use and zoned as such, which has lower allowable noise levels.

  • Impulse noise limits are set in different units (dBC) than continuous (dBA), what are the expected levels in dBC, as measured according to §249-2?

  • Noise estimates should be done at additional elevations to predict the noise coming into bedrooms.

  • The sound model should include all sources simultaneously, including car and truck traffic, backup generators, and truck backup alarms, which may be louder than those assumed in the existing study.

  • While the noise study assumes 8 active trucks, there may be more.  For example, the September Traffic Impact Study shows that from 5-6AM there are expected to be 10 tractor trailer trucks, 40 box trucks, and over 200 cars coming or going.

  • The noise study should not only consider expected immediate use, but also possible future use at full capacity, taking into account seasonality, growth, and the possibility of changes in tenants and ownership.


A follow-up report that incorporates the changes to the project is expected sometime in mid September, as per the schedule presented at the September 9th Planning Board meeting.


Ostergaard Acoustical Associates (OAA) Study

https://www.hudsonnh.gov/sites/default/files/fileattachments/planning_board/page/45611/preliminary20staff20report20-20may2027202020.pdf#page=188


Peer review by Harris Miller Miller & Hanson Inc. (HMMH)

https://www.hudsonnh.gov/sites/default/files/fileattachments/planning_board/meeting/packets/43062/staff_report_with_attachments_-_revised.pdf#page=20


OAA response to peer review and some written comments

https://www.hudsonnh.gov/sites/default/files/fileattachments/planning_board/meeting/packets/43062/revised_plans_studies.pdf#page=75


July 22 Planning Board Meeting

http://www.hudsonctv.com/CablecastPublicSite/show/9222?channel=3





Let Your Voice Be Heard!

Please send us your questions, comments, or concerns and we will do our best to share them with the appropriate stakeholders. Together we can save this town, Southern NH, and Northern Massachusetts from this Amazon facility!

Fill out the form or email us at savehudsonnh@gmail.com

  • Instagram
  • Facebook
Join Us
We do not own the rights to the photographs of the site plans and renderings. These pictures have been taken from: https://www.hudsonnh.gov/bc-pb/page/hudson-logistics-center-proposal and https://www.hudsonlogisticscenter.com